Giving the following information: Actual materials input used 8,500 KG Actual labor input used 3,500 hours Actual price of materials per unit $16 Actual price

Giving the following information:

  1. Actual materials input used                                              8,500 KG
  2. Actual labor input used                                                     3,500 hours
  3. Actual price of materials per unit                                     $16
  4. Actual price of labor per hour                                          $10
  5. Flexible budget price of materials per unit                       $18
  6. Flexible budget price of labor per hour                            $8.5
  7. Flexible budget units of materials                                    8,000KG
  8. Flexible budget hours of labor                                         3,200 hours


Required:

  1. The price variance for both materials and labor

  2. The efficiency variance for both materials and labor.

Step by Step Solution

3.36 Rating (152 Votes )

There are 3 Steps involved in it

Step: 1

Material Price Variance The difference between the Standard Price and Actual Price for the Actual Qu... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Microeconomics

Authors: Douglas Bernheim, Michael Whinston

2nd edition

73375853, 978-0073375854

More Books

Students also viewed these General Management questions