Glven the dato and information that follow, compute the total direct cost for each project duration. The indirect costs for each project duration are shown in the following table: To compress from time period 15 to time 14, crash the following activity(s) (You may select more than one answer. Single click the box with the question mark to produce a check mark for a correct answer and double click the box with the question mark to empty the box for a wrong answer. Any boxes left with a question mark will be automatically graded as incorrect.) To compress from time period 14 to time 13. crash the following activity(s): (You may select more than one answer. Single click the box with the question mark to produce a check mark for a correct answer and double click the box with the question mark to empty. the box for a wrong answer. Any boxes left with a question mark will be automatically graded as incorrect.) Q E ?* (?) () To compress from time period 13 to time 12, crash the following activity(s): (You may select more than one answer. Single click the box with the question mark to produce a check mark for a correct answer and double click the box with the question mark to empty the box for a wrong answer, Any boxes left with a question mark will be automatically graded as incorrect.) 28 ac (2) (2) 2. 20 (2) (2) What is the crash point of the network? What is the optimum cost-time schedule for the project? To compress from time period 15 to time 14, crash the following activity(s): (You may select more than one answer. Single click the box with the question mark to produce a check mark for a correct answer and double click the box with the question mark to empty the box for a wrong answer. Any boxes left with a question mark will be automatically graded as incorrect.)