Question
Golden Companys total overhead cost at various levels of activity are presented below: Month Machine-Hours Total Overhead Cost March 50,000 $209,100 April 40,000 $181,700 May
Golden Companys total overhead cost at various levels of activity are presented below: |
Month | Machine-Hours | Total Overhead Cost |
March | 50,000 | $209,100 |
April | 40,000 | $181,700 |
May | 60,000 | $236,500 |
June | 70,000 | $263,900 |
Assume that the overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 40,000 machine-hour level of activity is as follows: |
Utilities (variable) | $ | 60,000 |
Supervisory salaries (fixed) | 55,000 | |
Maintenance (mixed) | 66,700 | |
Total overhead cost | $ | 181,700 |
The company wants to break down the maintenance cost into its variable and fixed cost elements.
|
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access with AI-Powered Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started