Question
Goliath Quarry Products (GQP) was formed in the late 1960s in the UK to supply quarry equipment that required strong, robust machinery capable of crushing
Goliath Quarry Products (GQP) was formed in the late 1960’s in the UK to supply quarry equipment that required strong, robust machinery capable of crushing and screening 6000 tonnes of quarry rocks per day.
As the market developed GQP became a leading global supplier. GQP’s production facilities expanded from one factory site tofour4 factory sites in the UK. The main focus for GQP became new product development and ensuring that it maintained the quality and reliability synonymous with its brand.
In the last decade new low-cost competitors have entered the market and are starting to reduce GQP’s market share. GQP needs to concentrate on costs if it is going to sustain its market share leadership. GQP directors insist that it must maintain its brand image but achieve the same quality product at a lower cost. This may involve the use of low-cost country sourcing. Areas of concern for low-cost country sourcing are as follows:
- Poor quality product
- The passing of title
- Initial prices increasing once a commitment to supply has been made
- Orders not shipping on time and ‘premium’ transport arrangements having to be made
- Low-cost country suppliers subcontracting work and GQP not being aware that they have done this. This may result in poor quality.
The supply base
Simon Jones is one of GQP’s Supply Chain Managers and is responsible for the procurement of the fabrications for his site. The fabrications supplier base for GQP is mainly local. Simon realises that if he is to reduce costs he needs to expand his supply base, introduce competition and consider procurement from lower cost countries. Simon needs to review the range of fabrications and find product lines that would be suitable for low-cost country sourcing. Simon decides that the best way to do this is with the next planned new product introduction in 6 months’ time. Simon drafts a sourcing plan outlined in Table 1.
Table 1
Task | Description | Estimate duration (weeks) | Predecessor |
A | Identify a product line suitable of sourcing globally | 2 | |
B | Gather drawings, material and finish specification | 1 | A |
C | Determine the volumesover a medium/long-term period | 2 | A |
D | Analyse the supplier market locally andinternationally | 3 | A |
E | Review international sourcing options and select | 3 | D |
F | Send tender enquiry | 2 | B, C & F |
G | Visit potential suppliers | 2 | F |
H | Receive tenders | 4 | F |
I | Select potential suppliers | 1 | G & H |
J | Prototype build | 6 | I |
K | Airfreight prototype forapproval | 1 | J |
L | Gain Quality approval | 1 | K |
M | If approved thenFinal Negotiation and contract award | 2 | L |
Sourcing from low cost countries
GQP has a set time-frame of 6 months for the launch of its new product and needs to ensure no risk of failing to meet this deadline.
The local fabrication suppliers to GQP are very financially dependent on GQP with GQP being 80% of most of the local fabricator’s business. Simon believes that there may be collusion between the local suppliers when pricing. It is time for change and Simon believes that low-cost country sourcing may remove some of the complacency GQP feels they are experiencing with the local suppliers. Simon must ensure that any change to low-cost country sourcing must be seamless.
REQUIRED :
- For each of the Activities A to E suggest how the risks associated with international sourcing and the selection of global suppliers in the future may be reduced.
- Identify the critical path for the project.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started