Gomel engineering works on April 5 th , 2018 started production of 100 lawn mower of model EG-72 ordered by Capital Development Authority, Islamabad, vide
Gomel engineering works on April 5th , 2018 started production of 100 lawn mower of model EG-72 ordered by Capital Development Authority, Islamabad, vide Order No. 2119-M dated April 1, 2018 at a price of Rs. 3,600 per lawn mower. Production planning department allotted Job No. J-832-LM and instructed the factory to complete production by April 20, 2018. The factory completed production on April 18, 2018. The weekly materials requisitions summary No. MRS-16 and weekly labour cost analysis sheet LAS -16 following cost allocation to Job No. J-832-LM:
Dates | Particulars | Department 101 | Department 111 |
5/4/18 | Direct material | Rs.58,500 | Rs.11,700 |
11/4/18 | Rs.71,500 | Rs.14,300 | |
5/4/18 | Direct labour | Rs.13,500 | Rs.15,750 (900 hours) |
11/4/18 | Rs.16,500 | Rs.19,250 (1,100 hours) |
In department 101 factory overhead is applied 50% of direct labour cost and in department 111 @ Rs. 12 per direct labour hour. Marketing and administration expenses chargeable to the job were respectively 7.5% and 5% of the sale price. The lawn mowers were delivered to customer on April 22, 2018. Required: Prepare a Job Cost Sheet for Job No. J-832-LM using a proper header and format.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started