Gordon is a program manager. He has created a consolidated master file for Projects A. B. and C. Project B cannot start until the last
Gordon is a program manager. He has created a consolidated master file for Projects A. B. and C. Project B cannot start until the last milestone in Project A has been reached. He creates an interproject FS link between the last task in Project A and the First task in Project B. He notices that he is missing a row number in Project B. Why does this nappen