Graham Corporation's budgeted production schedule, by quarters, for the coming year is as follows: Quarter 1 = 27,500 units Quarter 2 = 24,000 units Quarter
Graham Corporation's budgeted production schedule, by quarters, for the coming year is as follows: Quarter 1 = 27,500 units Quarter 2 = 24,000 units Quarter 3 = 22,000 units Quarter 4 = 29,000 units Each unit of product requires three pounds of direct material. The company's policy is to begin each quarter with 30% of that quarter's direct materials production requirements. Graham expects to have 55,000 pounds of direct materials on hand at the beginning of Quarter 1. What would be Graham's budgeted direct materials purchases for the second quarter of the year?
Multiple Choice
-
73,800 pounds.
-
70,200 pounds.
-
68,850 pounds.
-
91,800 pounds.
-
72,000 pounds.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started