Grand Fender uses a standard cost system and provide the following information: (Click the icon to view the information.) Grand Fender allocates manufacturing overhead to production based on standard direct labor hours. Grand Fender reported the following actual results for 2018: actual number of fenders produced, 20,000; actual variable overhead, $4,560; actual fixed overhead, $27,000; actual direct labor hours, 440. Read the requirements. Requirement 1. Compute the overhead variances for the year: variable overhead cost variance, variable overhead efficiency variance, fixed overhead cost variance, and fixed overhead volume variance. Begin with the variable overhead cost and efficiency variances. Select the required formulas, compute the variable overhead cost and efficiency variances, and identify whether each variance is favorable (F) or unfavorable (U). (You may need to simply the formula based on the data provided. Abbreviations used: AC = actual cost; AQ = actual quantity; FOH = fixed overhead; SC = standard cost; SQ = standard quantity; VOH = variable overhead.) Formula Variance VOH cost variance VOH efficiency variance Now compute the fixed overhead cost and volume variances. Select the required formulas, compute the fixed overhead cost and volume variances, and identify whether each variance is favorable (F) or unfavorable (U). (Abbreviations used: AC = actual cost; AQ = actual quantity; FOH = fixed overhead; SC = standard cost; SQ = standard quantity.) Formula Variance FOH cost variance FOH volume variance Requirement 2. Explain why the variances are favorable or unfavorable. The variable overhead cost variance is because management spent than budgeted for the actual production. The variable overhead efficiency variance is because management used direct labor hours than standard and variable overhead is applied (incurred) based on direct labor.H Data Table X Static budget variable overhead $ 4,608 Static budget fixed overhead $ 23,040 Static budget direct labor hours 576 hours Static budget number of units 24,000 units Standard direct labor hours 0.024 hours per fender Print Done