Granite Company purchased a machine costing $134,000, terms 3/10, n/30. The machine was shipped FOB shipping point and freight charges were $3,400. The machine requires
Granite Company purchased a machine costing $134,000, terms 3/10, n/30. The machine was shipped FOB shipping point and freight charges were $3,400. The machine requires special mounting and wiring connections costing $11,400. When installing the machine, $2,900 in damages occurred. Compute the cost recorded for this machine assuming Granite paid within the discount period.