Question
Granite, Inc., is using Job Order Costing. Company currently is using a plant-wide overhead rate based on direct labor hours for the assignment of factory
Granite, Inc., is using Job Order Costing. Company currently is using a plant-wide overhead rate based on direct labor hours for the assignment of factory overhead costs to jobs. Company is expecting 8,000 direct labor hours for next year.
Due to intense competition accurate cost data has become very important. Accordingly, company is considering use of Activity Based Costing (ABC) for the assignment of factory overhead cost to jobs.
Company has identified the following activities causing the factory overhead costs and corresponding cost drivers for next year:
Activity Activity Cost | Activity Cost | Cost driver | Coat Driver Quantity |
Setup costs | 100000 | Number of setups | 400 |
Materials Ordering cost | 40000 | Number of orders | 2000 |
Maintenance | 200000 | # of Machine hours | 10000 |
Power | 20000 | # of Kilowatt hours | 100000 |
360000 |
The following is one of the jobs completed during the year: Job 500
Direct Materila | 3500 |
Direct labor | 2400 |
Unit Completed | 100 |
Direct Labor Hour | 100 |
Number of setups | 3 |
Number of Orders | 8 |
Machine Hours | 220 |
Power Kilowatt hours used | 160 |
a. Compute total cost of Job 500 under current system using a plant-wide overhead rate based on DLH. b. Compute total cost of Job 500 if Granite uses Activity Based Costing.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started