Greenwood Company manufactures two products14,000 units of Product Y and 6,000 units of Product Z. The company uses a plantwide overhead rate based on direct

Greenwood Company manufactures two products14,000 units of Product Y and 6,000 units of Product Z. The company uses a plantwide overhead rate based on direct labor-hours. It is considering implementing an activity-based costing (ABC) system that allocates all of its manufacturing overhead to four cost pools. The following additional information is available for the company as a whole and for Products Y and Z:

Activity Cost Pool Activity Measure Estimated Overhead Cost Expected Activity
Machining Machine-hours $ 195,000 10,000 MHs
Machine setups Number of setups $ 67,500 150 setups
Production design Number of products $ 79,000 2 products
General factory Direct labor-hours $ 245,000 10,000 DLHs

Activity Measure Product Y Product Z
Machining 7,500 2,500
Number of setups 50 100
Number of products 1 1
Direct labor-hours 7,500 2,500

2. Using the plantwide overhead rate, how much manufacturing overhead cost is allocated to Product Y and Product Z? (Round your intermediate calculations to 2 decimal places. Round your answers to the nearest dollar amount.)

What is the activity rate for the Machining activity cost pool? (Round your answer to 2 decimal places.)

What is the activity rate for the Machine Setups activity cost pool?

What is the activity rate for the Product Design activity cost pool?

What is the activity rate for the General Factory activity cost pool? (Round your answer to 2 decimal places.)

Which of the four activities is a batch-level activity?

  • Machining activity

  • General factory activity

  • Product design activity

  • Machine setups activity

Which of the four activities is a product-level activity?

  • Product design activity

  • Machine setups activity

  • General factory activity

  • Machining activity

    Using the ABC system, how much total manufacturing overhead cost would be assigned to Product Y? (Round your intermediate calculations to 2 decimal places. Round your answers to the nearest dollar amount.)

    Using the plantwide overhead rate, what percentage of the total overhead cost is allocated to Product Y and Product Z? (Round your intermediate calculations to 2 decimal places. Round your answers to 2 decimal places.)Using the ABC system, what percentage of the Machining costs is assigned to Product Y and Product Z? (Round your intermediate calculations to 2 decimal places. Round your answers to 2 decimal places.)

    Using the ABC system, what percentage of Machine Setups cost is assigned to Product Y and Product Z? (Round your intermediate calculations to 2 decimal places. Round your answers to 2 decimal places.)

    Using the ABC system, what percentage of the Product Design cost is assigned to Product Y and Product Z? (Round your answers to 2 decimal places.)

    Using the ABC system, what percentage of the General Factory cost is assigned to Product Y and Product Z? (Round your intermediate calculations and final answers to 2 decimal places.)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Performance Auditing Of Public Sector Property Contracts

Authors: Lori Keating

1st Edition

0566089998, 978-0566089992

More Books

Students also viewed these Accounting questions