Question
Greenwood Company manufactures two products15,000 units of Product Y and 7,000 units of Product Z. The company uses a plantwide overhead rate based on direct
Greenwood Company manufactures two products15,000 units of Product Y and 7,000 units of Product Z. The company uses a plantwide overhead rate based on direct labor-hours. It is considering implementing an activity-based costing (ABC) system that allocates all of its manufacturing overhead to four cost pools. The following additional information is available for the company as a whole and for Products Y and Z: Activity Cost Pool Activity Measure Estimated Overhead Cost Expected Activity Machining Machine-hours $ 210,100 11,000 MHs Machine setups Number of setups $ 45,100 110 setups Production design Number of products $ 75,000 2 products General factory Direct labor-hours $ 241,000 10,000 DLHs Activity Measure Product Y Product Z Machining 7,100 3,900 Number of setups 60 50 Number of products 1 1 Direct labor-hours 7,100 2,900 3.
What is the activity rate for the Machining activity cost pool? (Round your answer to 2 decimal places.)
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started