Question

1 Approved Answer

Greenwood Company manufactures two products15,000 units of Product Y and 7,000 units of Product Z. The company uses a plantwide overhead rate based on direct

Greenwood Company manufactures two products15,000 units of Product Y and 7,000 units of Product Z. The company uses a plantwide overhead rate based on direct labor-hours. It is considering implementing an activity-based costing (ABC) system that allocates all of its manufacturing overhead to four cost pools. The following additional information is available for the company as a whole and for Products Y and Z:

Activity Cost Pool Activity Measure Estimated Overhead Cost Expected Activity
Machining Machine-hours $ 213,400 11,000 MHs
Machine setups Number of setups $ 61,600 140 setups
Production design Number of products $ 78,000 2 products
General factory Direct labor-hours $ 244,000 10,000 DLHs

Activity Measure Product Y Product Z
Machining 6,400 4,600
Number of setups 60 80
Number of products 1 1
Direct labor-hours 7,400 2,600
Required:
1. What is the companys plantwide overhead rate? (Round your answer to 2 decimal places.)
2.

Using the plantwide overhead rate, how much manufacturing overhead cost is allocated to Product Y and Product Z? (Round your intermediate calculations to 2 decimal places and final answers to the nearest dollar amount.)

3.

What is the activity rate for the Machining activity cost pool? (Round your answer to 2 decimal places.)

4.

What is the activity rate for the Machine Setups activity cost pool? (Round your answer to 2 decimal places.)

5.

What is the activity rate for the Product Design activity cost pool? (Round your answer to 2 decimal places.)

6.

What is the activity rate for the General Factory activity cost pool? (Round your answer to 2 decimal places.)

7. Which of the four activities is a batch-level activity?
Machining activity
General factory activity
Product design activity
Machine setups activity

8. Which of the four activities is a product-level activity?
Machining activity
Machine setups activity
Product design activity
General factory activity

9.

Using the ABC system, how much total manufacturing overhead cost would be assigned to Product Y? (Round your intermediate calculations to 2 decimal places and final answer to the nearest dollar amount.)

10.

Using the ABC system, how much total manufacturing overhead cost would be assigned to Product Z? (Round your intermediate calculations to 2 decimal places and final answer to the nearest dollar amount.)

11.

Using the plantwide overhead rate, what percentage of the total overhead cost is allocated to Product Y and Product Z? (Round your answers to 2 decimal places.)

12.

Using the ABC system, what percentage of the Machining costs is assigned to Product Y and Product Z? (Round your answers to 2 decimal places.)

13.

Using the ABC system, what percentage of Machine Setups cost is assigned to Product Y and Product Z? (Round your answers to 2 decimal places.)

14

Using the ABC system, what percentage of the Product Design cost is assigned to Product Y and Product Z? (Round your answers to 2 decimal places.)

15.

Using the ABC system, what percentage of the General Factory cost is assigned to Product Y and Product Z? (Round your answers to 2 decimal places.)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Students also viewed these Accounting questions