Greg contracts to build a storage shed for Haney, who pays Greg in advance, but Greg completes only half the work. Haney pays Ipswich $500
Greg contracts to build a storage shed for Haney, who pays Greg in advance, but Greg completes only half the work. Haney pays Ipswich $500 to finish the shed. If Haney sues Greg, what would be the measure of recovery?
a.
$500 plus consequential damages.
b.
lost profit.
c.
Return of the purchase price.
d.
$500.