Guillermo Santiago has been developing a project plan and hasidentified the following tasks, precedence relations, normal taskdurations, and resource requirements.The critical question is whether begin{tabular}{c|c|c|c}
Guillermo Santiago has been developing a project plan and hasidentified the following tasks, precedence relations, normal taskdurations, and resource requirements.The critical question is whether \begin{tabular}{c|c|c|c} Task & Predecessors & Task Duration & Resource Required \\ \hline start & & 0 & 0 \\ A & start & 31 & 8 \\ B & A & 34 & 8 \\ C & A & 37 & 6 \\ D & A & 29 & 2 \\ E & B & 14 & 3 2 answers