Habelt Company's labor cost per unit is $45 (3 hours x $15 per hour). For the month of May, Habelt Company had 3,600 hours of
Habelt Company's labor cost per unit is $45 (3 hours x $15 per hour). For the month of May, Habelt Company had 3,600 hours of direct labor with an hourly cost of $40.50 per hour and made 1,300 units of finished product. Find total, price, and quantity variance.
Figure out what the total, price, and quantity variances are from the given information.