Haggrun Co has two contracts in progress, the details of which are as follows. Happy (profitable) Grumpy (loss-making) $000 $000 Total contract revenue 300 300
Haggrun Co has two contracts in progress, the details of which are as follows.
| Happy (profitable) | Grumpy (loss-making) |
| $000 | $000 |
Total contract revenue | 300 | 300 |
Costs incurred to date | 90 | 150 |
Estimated costs to completion | 135 | 225 |
Payments invoiced and received | 116 | 116 |
Haggrun measures satisfaction of performance obligations based on percentage of work certified as complete.
Required: Show extracts from the statement of profit or loss and other comprehensive income and the statement of financial position for each contract, assuming they are both certified as:
(1) 40% complete; and
(2) 36% complete
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started