Question
Hamaya, a Japanese transportation company, is planning to build a new distribution centre in Kowloon district. The project manager proposed the following work breakdown structure
Hamaya, a Japanese transportation company, is planning to build a new distribution centre in Kowloon district. The project manager proposed the following work breakdown structure with precedence requirements, estimated normal and crash times, and normal and crash costs.
Activity | Immediate Predecessor | Normal Time (Weeks) | Crash Time (Weeks) | Normal Cost | Crash Cost |
A | None | 5 | 3 | 18,000 | 30,000 |
B | A | 10 | 7 | 109,500 | 120,000 |
C | A | 4 | 3 | 9,000 | 10,000 |
D | A | 7 | 5 | 56,000 | 60,000 |
E | B | 8 | 5 | 90,000 | 97,500 |
F | B | 6 | 4 | 12,000 | 15,000 |
G | C, D | 7 | 4 | 25,000 | 32,500 |
H | G | 3 | 2 | 80,000 | 83,000 |
I | E, F, H | 9 | 5 | 110,000 | 138,000 |
|
|
|
|
|
|
(1) From the data shown, when the project will be finished at normal cost? Assume a linear cost per week shortened, determine how to finish the project as soon as possible at the minimum cost. Show, step by step, how you arrived at your schedule. No need not to show the final project network.
(2) If Hamaya is renting a temporary warehouse for $8,100 per week now, when should this warehouse construction project be completed in order to be most economical? Why?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started