Hamilton Corp. constructed a building during 2020. The total cost of the building was $18,736,685. Hamilton's weighted average accumulated expenditures on the building qualifying for
Hamilton Corp. constructed a building during 2020. The total cost of the building was $18,736,685. Hamilton's weighted average accumulated expenditures on the building qualifying for capitalized interest during the year totaled $10,537,006. Hamilton borrowed $13,242,717 to at 9% finance the construction.How much interest should Hamiton capitalize for 2020? Please round your answer to the nearest dollar.