Hannibal Steel Company has a Transport Services Department that provides trucks to haul ore from the company's mine to its two steel mills-the Northern Plant and the Southern Plant Budgeted costs for the Transport Services Department total $197,400 per year, consisting of $0.22 per ton variable cost and $147,400 fixed cost. The level of fixed cost is determined by peak-period requirements. During the peak period, the Northern Plant requires 67% of the Transport Services Department's capacity and the Southern Plant requires 33% During the year, the Transport Services Department actually hauled 114,000 tons of ore to the Northern Plant and 59,400 tons to the Southern Piant. The Transport Services Department incurred $377,000 in cost during the year, of which $53,800 was variable cost and $323,200 was fixed cost. Required: 1. How much of the Transport Services Department's variable costs should be charged to each plant? 2. How much of the $323,200 in fixed cost should be charged to each plant? 3. Should any of the Transport Services Department's actual total cost of $377,000 be treated as a spending variance and not charged to the plants? Complete this question by entering your answers in the tabs below. Required 1 Required 2 Required 3 How much of the Transport Services Department's variable costs should be charged to each plant? Variable cost charged to Northern Plant Variable cont charged to Southern Plant es Complete this question by entering your answers in the tabs below. Required 1 Required 2 Required 3 How much of the fixed cost should be charged to each plant? Fixed cost charged to Northern Plant Fixed cost charged to Southern Plant Complete this question by entering your answers in the tabs below. Required 1 Required 2 Required 3 Should any of the Transport Services Department's actual total cost of $377,000 be treated as a spending variance and not charged to the plants? Spending variance