Question

1 Approved Answer

Happy Dam Co obtained a contract to build the dam for $16.8 million. The contract is estimated to be completed at a cost of $14

Happy Dam Co obtained a contract to build the dam for $16.8 million. The contract is estimated to be completed at a cost of $14 million. The following information related to the contract is presented: (in $)

2020 2021 2022
The costs incurred are issued until the year: 5.760.000 10.220.000 14.600.000
Estimated cost of next settlement 7.040.000 4.380.000 -
Current year billing 7.000.000 6.400.000 B
Cash received in the current year C 5.750.000 4.750.000

Required:

  1. Calculate the percentage of completions for 3 years
  2. Keep all the necessary journals if the company uses the percentage of completion method!

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Statistical Analysis Microsoft Excel 2013

Authors: Conrad Carlberg

1st Edition

0789753111, 9780789753113

More Books

Students also viewed these Accounting questions

Question

What is the biggest challenge facing the organization?

Answered: 1 week ago

Question

3. Give examples of four fair disciplinary practices.

Answered: 1 week ago

Question

4. Explain how to use fair disciplinary practices.

Answered: 1 week ago