Happy Dam Co obtained a contract to build the dam for $16.8 million. The contract is estimated to be completed at a cost of $14
Happy Dam Co obtained a contract to build the dam for $16.8 million. The contract is estimated to be completed at a cost of $14 million. The following information related to the contract is presented: (in $)
2020 | 2021 | 2022 | |
The costs incurred are issued until the year: | 5.760.000 | 10.220.000 | 14.600.000 |
Estimated cost of next settlement | 7.040.000 | 4.380.000 | - |
Current year billing | 7.000.000 | 6.400.000 | B |
Cash received in the current year | C | 5.750.000 | 4.750.000 |
Required:
- Calculate the percentage of completions for 3 years
- Keep all the necessary journals if the company uses the percentage of completion method!
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started