Harlen Company is involved in a competitive bidding situation. The following costs are anticipated for a project to be bid with the City of Crimson:
Harlen Company is involved in a competitive bidding situation. The following costs are anticipated for a project to be bid with the City of Crimson:
Direct material $
Direct labor
Allocated variable overhead
Allocated fixed cost
Which of the following cost figures should be used in setting a minimum bid price if Harlen has excess capacity?
Multiple Choice
$
$
$
$
None of the answers is correct.