Hart manufacturing operates an automated steel fabrication process. For one operation, Hart has found that 55% of total throughput time is spent on non-value-added activities.
Hart manufacturing operates an automated steel fabrication process. For one operation, Hart has found that 55% of total throughput time is spent on non-value-added activities. Delivery cycle time is 14 hours, wait time during the production process is 3 hours, queue time prior to starting the production process is 2 hours and inspection time is 1.20 hours.
A- What is the number of hours associated with process time?
B- What is the number of hours associated with move time?
C- What is the total number of hours associated with manufacturing cycle time?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started