Hartman Co. submitted a $350,000 Request for Equitable Adjustment (REA) plus a 30 day time extension request as a result of this delay. What clause
Hartman Co. submitted a $350,000 Request for Equitable Adjustment (REA) plus a 30 day time extension request as a result of this delay. What clause allows the contracting officer to issue a modification to the contract if this REA is found to have merit? FAR 52.243-4, Changes FAR 52.236-15, Schedules for Construction Contracts FAR 52.233-1, Disputes FAR 52.245-1, Government Property