Haver Company currently pays an outside supplier $53 per unit for a part for one of its products. Haver is considering two alternative methods of making the part. Method 1 for making the part would require direct materials of $24 per unit, direct labor of $27 per unit, and incremental overhead of $3 per unit. Method 2 for making the part would require direct materials of $24 per unit, direct labor of $21 per unit, and incremental overhead of $7 per unit. Required: 1. Compute the cost per unit for each alternative method of making the part. 2. Should Haver make or buy the part? If Haver makes the part, which production method should it use? Complete this question by entering your answers in the tabs below. Required 1 Required 2 Compute the cost per unit for each alternative method of making the part Make with Method Cost per unit Mako with Method 2 Buy Cost per unit Req Required 2 > Haver Company currently pays an outside supplier $53 per unit for a part for one of its products. Haver is cons methods of making the part. Method 1 for making the part would require direct materials of $24 per unit, direct and incremental overhead of $3 per unit. Method 2 for making the part would require direct materials of $24 pe $21 per unit, and incremental overhead of $7 per unit Required: 1. Compute the cost per unit for each alternative method of making the part. 2. Should Haver make or buy the part? If Haver makes the part, which production method should it use? Complete this question by entering your answers in the tabs below. Required 1 Required 2 Should Haver make or buy the part? If Haver makes the part, which production method should it use? Should Haver make or buy the part? of Haver makes the part, which production method should it use?