Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

Hawke Skateboards is considering building a new plant. Bob Skerritt, the company's marketing manager, is an enthusiastic supporter of the new plant. Lucy Liu, the

image text in transcribed

Hawke Skateboards is considering building a new plant. Bob Skerritt, the company's marketing manager, is an enthusiastic supporter of the new plant. Lucy Liu, the company's chief financial officer, is not so sure that the plant is a good idea. Currently, the company purchases its skateboards from foreign manufacturers. The following figures were estimated regarding the construction of a new plant.

Cost of plant: $3,920,000

Estimated useful life: 15 years

Annual cash inflows: 3,920,000

Salvage value: $1,960,000

Annual cash outflows: 3,469,000

Discount rate: 11%

Bob Skerritt believes that these figures understate the true potential value of the plant. He suggests that by manufacturing its own skateboards the company will benefit from a "buy American" patriotism that he believes is common among skateboarders. He also notes that the firm has had numerous quality problems with the skateboards manufactured by its suppliers. He suggests that the inconsistent quality has resulted in lost sales, increased warranty claims, and some costly lawsuits. Overall, he believes sales will be $196,000 higher than projected above, and that the savings from lower warranty costs and legal costs will be $59,000 per year. He also believes that the project is not as risky as assumed above, and that a 9% discount rate is more reasonable.

  • Compute the net present value of the project based on the original projections.(If the net present value is negative, use either a negative sign preceding the numbere.g.-45 or parenthesese.g.(45).Round factor values to 5 decimal places, e.g. 1.25124 and final answer to 0 decimal places, e.g. 5,275.)

Net Present Value:

  • Compute the net present value incorporating Bob's estimates of the value of the intangible benefits, but still using the 11% discount rate.(If the net present value is negative, use either a negative sign preceding the numbere.g.-45 or parenthesese.g.(45).Round factor values to 5 decimal places, e.g. 1.25124 and final answer to 0 decimal places, e.g. 5,275.)

Net Present Value:

  • Compute the net present value using the original estimates, but employing the 9% discount rate that Bob suggests is more appropriate.(If the net present value is negative, use either a negative sign preceding the numbere.g.-45 or parenthesese.g.(45).Round factor values to 5 decimal places, e.g. 1.25124 and final answer to 0 decimal places, e.g. 5,275.)

Net Present Value:

image text in transcribedimage text in transcribed
S edugen.wileyplus.com C + WileyPLUS Kimmel, Accounting, 7e Help | System Announcements CALCULATOR PRINTER VERSION BACK NEXT ASSIGNMENT RESOURCES Expand Your Critical Thinking 25-02 a-c GB519 Excel Track Hawke Skateboards is considering building a new plant. Bob Skerritt, the company's marketing manager, is an enthusiastic supporter of the new plant. Lucy Liu, the company's chief financial officer, is Module 4 - Part 7- not so sure that the plant is a good idea. Currently, the company purchases its skateboards from foreign manufacturers. The following figures were estimated regarding the construction of a new Competency plant. Expand Your Critical Thinking 25-02 a-c Cost of plant $3,920,000 Estimated useful life 15 years Expand Your Critical Thinking 25-02 d Annual cash inflows 3,920,000 Salvage value $1,960,000 (Essay) Annual cash outflows 3,469,000 Discount rate 1% Review Score Review Results by Study Bob Skerritt believes that these figures understate the true potential value of the plant. He suggests that by manufacturing its own skateboards the company will benefit from a "buy American" Objective patriotism that he believes is common among skateboarders. He also notes that the firm has had numerous quality problems with the skateboards manufactured by its suppliers. He suggests that the inconsistent quality has resulted in lost sales, increased warranty claims, and some costly lawsuits. Overall, he believes sales will be $196,000 higher than projected above, and that the savings from lower warranty costs and legal costs will be $59,000 per year. He also believes that the project is not as risky as assumed above, and that a 9% discount rate is more reasonable. Click here to view the factor table. Answer each of the following. Your answer is partially correct. Try again. Compute the net present value of the project based on the original projections. (If the net present value is negative, use either a negative sign preceding the number e.g. -45 or parentheses e.g. (45). Round factor values to 5 decimal places, e.g. 1.25124 and final answer to 0 decimal places, e.g. 5,275.) Net present value -676,904 Should the project be accepted? The project should be rejected LINK TO TEXT Your answer is partially correct. Try again. Compute the net present value incorporating Bob's estimates of the value of the intangible benefits, but still using the 11% discount rate. (If the net present value is negative, use either a negative sign preceding the number e.g. -45 or parentheses e.g. (45). Round factor values to 5 decimal places, e.g. 1.25124 and final answer to 0 decimal places, e.g. 5,275.) Net present value 1,156,775 S edugen.wileyplus.com C + WileyPLUS Kimmel, Accounting, 7e Help | System Announcements CALCULATOR PRINTER VERSION 1 BACK NEXT ASSIGNMENT RESOURCES GB519 Excel Track Module 4 - Part 7- Should the project be accepted? Competency Expand Your Critical Thinking 25-02 a-c The project should be rejected Expand Your Critical Thinking 25-02 d (Essay) LINK TO TEXT Review Score Review Results by Study Objective Your answer is partially correct. Try again. Compute the net present value incorporating Bob's estimates of the value of the intangible benefits, but still using the 11% discount rate. (If the net present value is negative, use either a negative sign preceding the number e.g. -45 or parentheses e.g. (45). Round factor values to 5 decimal places, e.g. 1.25124 and final answer to 0 decimal places, e.g. 5,275.) x Net present value 1,156,775 Should the project be accepted? The project should be accepted LINK TO TEXT Your answer is partially correct. Try again. Compute the net present value using the original estimates, but employing the 9% discount rate that Bob suggests is more appropriate. (If the net present value is negative, use either a negative sign preceding the number e.g. -45 or parentheses e.g. (45). Round factor values to 5 decimal places, e.g. 1.25124 and final answer to 0 decimal places, e.g. 5,275.) Net present value 284,624 Should the project be accepted? The project should be accepted + Click if you would like to Show Work for this question: Open Show Work

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Payroll Accounting 2020

Authors: Bernard J. Bieg, Judith A. Toland

30th edition

357117174, 978-0357117170

More Books

Students also viewed these Accounting questions

Question

What do you think you will bring to the organization?

Answered: 1 week ago

Question

What is management growth? What are its factors

Answered: 1 week ago