Hawkins Corporation began construction of a motel on March 31, 2018. The project was completed on April 30, 2019. No new loans were required to
Hawkins Corporation began construction of a motel on March 31, 2018. The project was completed on April 30, 2019. No new loans were required to fund construction. Hawkins does have the following two interest-bearing liabilities that were outstanding throughout the construction period: $5,600,000, 6% note $10,240,000, 10% bonds Construction expenditures incurred were as follows:
March 31, 2018 | $ | 3,460,000 | |
June 30, 2018 | 5,460,000 | ||
November 30, 2018 | 1,692,000 | ||
February 28, 2019 | 2,460,000 | ||
The companys fiscal year-end is December 31. Required: Calculate the amount of interest capitalized for 2018 and 2019
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started