he Executive team asks for a timeline that displays milestones and key project tasks. Which of the following approaches is best for showing this information?
he Executive team asks for a timeline that displays milestones and key project tasks. Which of the following approaches is best for showing this information? Take the Executive team to Milestones for a nice lunch Use callouts for milestones, and use bars for key tasks Use callouts for milestones and key tasks Use bars for milestones, and use callouts for key tasks