he following list represents CPM network of a project. Activity Normal time ( day ) Crash time ( days ) Normal cost Crash cost Predecessor

he following list represents CPM network of a project.
Activity Normal time (day) Crash time (days)
Normal cost
Crash cost Predecessor
A 86 $1,000 $1,600---
B 107 $2,000 $2,600---
C 54 $500 $1,000 A
D 97 $4,000 $4,200 A, B
E 21 $3,000 $4,000 C, D
Which activity should be crashed first to cut one day from the project's duration; how much is added to project cost?
Question 11 options:
D; $100
B; $200
E; $1000
C; $100

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Green Practices And Supply Chain Performance In Government Hospitals In Nairobi Kenya

Authors: David Mbaabu

1st Edition

3668622574, 9783668622579

More Books

Students also viewed these General Management questions

Question

What is push strategy ?

Answered: 1 week ago