Question
1 Approved Answer
he probability of a project being late with a contracted completion time of 35 days, a mean duration of 38 days and a VARIANCE of
he probability of a project being late with a contracted completion time of 35 days, a mean duration of 38 days and a VARIANCE of 7.8 is: A. 92% B. 86% C. 64% D. 68%