Hector Company purchased land for an office site by paying $900,000 cash on January 1, 2019. Hector began construction on the office building on January
Hector Company purchased land for an office site by paying $900,000 cash on January 1, 2019. Hector began construction on the office building on January 1 and finished on December 31, 2019. The following expenditures were incurred for construction:
Date Expenditures
January 1, 2019 $600,000
April 1, 2019 $840,000
October 1, 2019 $1,500,000
December 1, 2019 $2,400,000
Calculate the weighted-average accumulated expenditure on the project during the year 2019 was:
Group of answer choices
$1,805,000.
$1,880,000.
$1,735,000.
$1,800,000.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started