Hector Company purchased land for an office site by paying $900,000 cash on January 1, 2019. Hector began construction on the office building on January

Hector Company purchased land for an office site by paying $900,000 cash on January 1, 2019. Hector began construction on the office building on January 1 and finished on December 31, 2019. The following expenditures were incurred for construction:

Date Expenditures

January 1, 2019 $600,000

April 1, 2019 $840,000

October 1, 2019 $1,500,000

December 1, 2019 $2,400,000

Calculate the weighted-average accumulated expenditure on the project during the year 2019 was:

Group of answer choices

$1,805,000.

$1,880,000.

$1,735,000.

$1,800,000.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Auditing a business risk appraoch

Authors: larry e. rittenberg, bradley j. schwieger, karla m. johnston

6th Edition

9780324645095, 324645090, 978-0324375589

More Books

Students also viewed these Accounting questions

Question

Understand a department managers role in locating job candidates

Answered: 1 week ago