Question
Heineken Co. began a construction project in 2019 at a total contract price of $150 million. The project is scheduled for completion by 2021. During
Heineken
Co. began a construction project in 2019 at a total contract price of
$150 million.
The
project is scheduled for completion by 2021. During 2019, Heineken
incurred $36 million of
costs and estimates an additional $84 million of costs to complete the project. In 2020, Heineken
incurred costs of $58.5 million and estimated an additional $40.5 million in costs to complete the
project. Heineken
recognizes revenue on
all contracts
over time, as the project is being completed
by using the cost to cost approach.
_____ 13.In their 2020 income statement
, Heineken
would:
A)
Recognized $15 million gross profit on the project.
B)
Recognized $13.5 million gross profit on the project.
C)
Recognized $6 million gross profit on the project.
D)
Recognized $1.5 million gross profit on the project.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started