Helen has just learned that she needs to reduce the duration of her project to meet an imposed deadline. She has calculated the crash cost
Helen has just learned that she needs to reduce the duration of her project to meet an imposed deadline. She has calculated the crash cost per unit and knows the maximum units each activity can be reduced. What the next step? Multiple Choice Find the activity with the lowest crash cost ices Calculate the optimum cost-time point Calculate the crash point Identify the critical path Find the activity with the highest crash cost