hello, Can you make a gantt chart according to to following informations? Tasks start date days needs completion 1.1.1 Excavation 1/05/2024 15 16/05/2023 1.1.2 Concrete
hello,
Can you make a gantt chart according to to following informations?
Tasks | start date | days needs | completion |
1.1.1 Excavation | 1/05/2024 | 15 | 16/05/2023 |
1.1.2 Concrete Filling | 17/05/2024 | 15 | 04/06/2024 |
1.1.3 Site Pavement | 05/06/2024 | 15 | 21/06/2023 |
1.1.4 Substructure | 22/06/2023 | 7 | 30/06/2023 |
1.2.1 Floor framing | 01/07/2024 | 15 | 15/07/2024 |
1.2.2 install roofing materials | 17/07/2024 | 10 | 26/07/2024 |
1.2.3 Seal and waterproof | 28/07/2024 | 7 | 05/08/2024 |
1.3.1 Electrical | 07/08/2024 | 10 | 18/08/2024 |
1.3.2 Plumbing | 20/08/2024 | 10 | 01/09/2024 |
1.3.3 Kitchen works | 05/09/2024 | 20 | 30/09/2024 |
1.3.4 Bathrooms works | 01/10/2024 | 25 | 26/10/2024 |
1.3.5 Painting | 28/10/2024 | 10 | 06/11/2024 |
1.4.1 HVAC | 07/11/2024 | 10 | 16/11/2024 |
1.4.2 Insulation | 08/11/2024 | 3 | 11/11/2024 |
1.6.1 Landscaping | 20/11/2024 | 15 | 05/12/2024 |
1.6.2 Exterior painting | 07/12/2024 | 10 | 17/12/2024 |
1.6.3 Final inspection | 25/12/2024 | 2 | 27/12/2024 |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started