Question
Use Microsoft Project OR a project management software to set up a project based on the list of tasks and precedence relationships shown in the
- Use Microsoft Project OR a project management software to set up a project based on the list of tasks and precedence relationships shown in the table below. Address the questions below. Organize the project into 4 main phases: Analysis (1-4), Design (5-7), Construction (8-9) and Implementation (10-11) (this will change task numbers listed below).
Task | Description | Duration (days) | Predecessor |
1 | Preliminary investigation | 2 | - |
2 | Problem analysis | 2 | 1 |
3 | Data requirements analysis | 3 | 2 |
4 | Process requirements analysis | 6 | 3 |
5 | Database design | 3 | 3 |
6 | Interface design | 4 | 3,4,5 |
7 | Process and program design | 4 | 3,5,6 |
8 | Programming and unit testing | 7 | 5,6,7 |
9 | System testing | 3 | 8 |
10 | Installation | 2 | 9 |
11 | Configure | 1 | 10 |
Provide answers here to the questions below:
- Set the project start date for February 10, 2020
- What will be the end date of the project?
- How many days will it take to complete the Analysis phase?
- How many days will it take to complete the Design phase?
- How many days will it take to complete the Construction phase?
- How many days will it take to complete the Implementation phase?
- How many days will it take to complete the entire project?
- What tasks are on the critical path?
- Explain the critical path
- Paste a screenshot of Gantt chart view– be sure to include task name, duration, start, finish, predecessors and calendar
- Paste a screenshot of Network diagram view
2. Something has changed in the above project. Interface design assumed of a Windows user interface, but now management has decided the system should also support a web browser interface. You estimate that the web screen will require an additional two days to design, prototype, and test. Make this revision to your original duration estimate for “Interface design” in Microsoft Project.
- Review the Gantt chart, Network diagram and critical tasks report
- Explain what this change does to the schedule and projected project completion date? Be specific.
Step by Step Solution
3.47 Rating (160 Votes )
There are 3 Steps involved in it
Step: 1
What will be the end date of the project March 102020 How many days will it take to complete the Ana...Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Document Format ( 2 attachments)
635d61bf1625a_175076.pdf
180 KBs PDF File
635d61bf1625a_175076.docx
120 KBs Word File
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started