Hello! Please help me find the target completion time in weeks and the total savings. Please show work. I believe the critical path is B-D-F-G-H,

Hello! Please help me find the target completion time in weeks and the total savings. Please show work. I believe the critical path is B-D-F-G-H, and the normal completion time is 36 weeks. Not sure what to do from here. Thanks.

You are the project manager of the software installation project in the table below. You would like to find the minimum-cost schedule for your project. There is a $1,000-per-week penalty for each week the project is delayed beyond week 25. In addition, your project team determined that indirect project costs are$1,500 per week.

image text in transcribed

a. What would be your target completion week? The target completion week is week (Enter your response as an integer.) b. How much would you save in total project costs with your schedule? Total Savings =$ . (Enter your response as an integer.)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Introduction to Operations and Supply Chain Management

Authors: Cecil B. Bozarth, Robert B. Handfield

3rd edition

132747324, 978-0132747325

More Books

Students also viewed these General Management questions