help An organization planned to use $44 of material per unit of product but it actually used
Fantastic news! We've Found the answer you've been seeking!
Question:
help
An organization planned to use $44 of material per unit of product but it actually used $42 of material per unit of product. The organization planned to make 1.200 units of product, but actually made 1,000 units. What is the flexible budget amount for material? A) $48,000 B) $42,000 C) $52,800 D) $44.000