Here are the cash flows for a project under consideration: C0 C1 C2 -7,660 +5.600 +19,440 a. calculate the project's NPV for discount rates of
Here are the cash flows for a project under consideration:
C0 C1 C2
-7,660 +5.600 +19,440
a. calculate the project's NPV for discount rates of 0, 50%, and 100%
b. What is the IRR of the project?
IRR= %