Here are the data for a time - cost CPM scheduling model analysis. The time is in days and the costs include both direct and

Here are the data for a time-cost CPM scheduling model analysis. The time is in days and the costs include both direct and indirect costs.
Activity Immediate Predecessor Normal Time Crash Time Normal Cost Crash Cost
A None 32 $ 200 $ 400
B A 43 $ 300 $ 600
C A 11 $ 300 $ 300
D B and C 32 $ 500 $ 550
E D 21 $ 500 $ 900
If you crash this project to reduce the total time by one day, what is the total time of the project and total cost?
Multiple Choice
Total time is 13 days, total cost is $1,500.
Total time is 12 days, total cost is $2,000.
Total time is 12 days, total cost is $2,300.
Total time is 11 days, total cost is $1,850.
Total time is 11 days, total cost is $2,350.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Understanding And Managing Public Organizations

Authors: Hal G. Rainey, Sergio Fernandez, Deanna Malatesta

6th Edition

ISBN: 1119705894, 978-1119705895

More Books

Students also viewed these General Management questions