Here is a list of processes and their running times in milliseconds: A: 8 0 0 , B: 6 0 0 , C: 1 0

Here is a list of processes and their running times in milliseconds:
A:800, B:600, C:100, D:900, E:300
If the context switch time is zero, compute the time that it takes for each process to finish assuming that the time slice is set to 100ms
Process A : Answer 1 Question 1
2500
ms
Process B : Answer 2 Question 1
2100
ms
Process C : Answer 3 Question 1
300
ms
Process D : Answer 4 Question 1
2600
ms
Process E : Answer 5 Question 1
1300
ms
What would be the average efficiency of the processor if the context switching time was set to 10ms? Enter a rounded integer value as your answer. Answer 6 Question 1
%

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Graph Database Modeling With Neo4j

Authors: Ajit Singh

2nd Edition

B0BDWT2XLR, 979-8351798783

More Books

Students also viewed these Databases questions

Question

Is WACC consistent with a target debtequity ratio? Explain.

Answered: 1 week ago

Question

Sell the quality of your brand or products.

Answered: 1 week ago

Question

1.The difference between climate and weather?

Answered: 1 week ago

Question

1. What is Fog ?

Answered: 1 week ago

Question

How water vapour forms ?

Answered: 1 week ago

Question

What is Entrepreneur?

Answered: 1 week ago

Question

Which period is known as the chalolithic age ?

Answered: 1 week ago