Question
Here is some data for Project XYZ Budget $ 5,276 thousand Start Workday 7 Finish Workday 109 Reporting Day 34 Earned Value $ 262 thousand
Here is some data for Project "XYZ"
Budget | $ 5,276 thousand |
Start Workday | 7 |
Finish Workday | 109 |
Reporting Day | 34 |
Earned Value | $ 262 thousand |
Planned Value | $ 364 thousand |
Actual Cost | $ 741 thousand |
Using a "Do-Nothing" forecast, estimate the extra amount of money that will need to be added to (or subtracted from) the budget, in thousands of dollars, rounded to the nearest integer number of thousands. The allowed error margin is 2% or 1 thousand dollars, whichever is larger.
Step by Step Solution
3.31 Rating (160 Votes )
There are 3 Steps involved in it
Step: 1
DoNothing forecast technique is a very simple technique of forecasting In this technique of f...Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get StartedRecommended Textbook for
A Pathway To Introductory Statistics
Authors: Jay Lehmann
1st Edition
0134107179, 978-0134107172
Students also viewed these Mathematics questions
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
View Answer in SolutionInn App