Question

1 Approved Answer

Here is some data for Project XYZ Budget $ 5,276 thousand Start Workday 7 Finish Workday 109 Reporting Day 34 Earned Value $ 262 thousand

Here is some data for Project "XYZ"

Budget$ 5,276 thousand
Start Workday7
Finish Workday109
Reporting Day34
Earned Value$ 262 thousand
Planned Value$ 364 thousand
Actual Cost$ 741 thousand


Using a "Do-Nothing" forecast, estimate the extra amount of money that will need to be added to (or subtracted from) the budget, in thousands of dollars, rounded to the nearest integer number of thousands. The allowed error margin is 2% or 1 thousand dollars, whichever is larger.


Step by Step Solution

3.31 Rating (160 Votes )

There are 3 Steps involved in it

Step: 1

DoNothing forecast technique is a very simple technique of forecasting In this technique of f... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

A Pathway To Introductory Statistics

Authors: Jay Lehmann

1st Edition

0134107179, 978-0134107172

More Books

Students also viewed these Mathematics questions

Question

What is group shift? What is its effect on decision-making quality?

Answered: 1 week ago

Question

Discuss what happens when children develop two languages.

Answered: 1 week ago

Question

Evaluate x + zs for x = 15, z = -2, s = 5.

Answered: 1 week ago

Question

Evaluate the following, accurate to the nearest cent.

Answered: 1 week ago

Question

Evaluate each of the following, accurate to the nearest cent.

Answered: 1 week ago

Question

Evaluate the answers accurate to the cent.

Answered: 1 week ago