Here is the Activity Network Project Schedule for the Employee Training Management System project, including task relationships, durations, start dates, and end dates: Task ID

Here is the Activity Network Project Schedule for the Employee Training Management System project, including task relationships, durations, start dates, and end dates:

Task ID Task Name Predecessor(s) Duration (days) Start Date End Date
1.1 Project Management - 10 2024-03-01 2024-03-12
1.1.1 Project Planning - 2 2024-03-01 2024-03-02
1.1.2 Project Execution 1.1.1 5 2024-03-03 2024-03-08
1.1.3 Project Monitoring and Control 1.1.2 2 2024-03-09 2024-03-10
1.1.4 Project Closure 1.1.3 1 2024-03-11 2024-03-12
1.2 Requirements Gathering 1.1 7 2024-03-13 2024-03-19
1.2.1 Business Requirements 1.2 3 2024-03-13 2024-03-15
1.2.2 Technical Requirements 1.2 4 2024-03-16 2024-03-19
1.3 Design 1.2 14 2024-03-20 2024-04-02
1.3.1 System Architecture 1.3 5 2024-03-20 2024-03-24
1.3.2 User Interface Design 1.3.1 4 2024-03-25 2024-03-29
1.3.3 Database Design 1.3.2 5 2024-03-30 2024-04-02
1.4 Development 1.3 30 2024-04-03 2024-05-02
1.4.1 Front-end Development 1.4 15 2024-04-03 2024-04-17
1.4.2 Back-end Development 1.4.1 10 2024-04-18 2024-04-27
1.4.3 Integration and Testing 1.4.2 5 2024-04-28 2024-05-02
1.5 Deployment 1.4.3 7 2024-05-03 2024-05-09
1.5.1 User Acceptance Testing 1.5 3 2024-05-03 2024-05-05
1.5.2 Deployment Planning 1.5.1 2 2024-05-06 2024-05-07
1.5.3 Deployment Execution 1.5.2 2 2024-05-08 2024-05-09
1.6 Maintenance and Support 1.5.3 30 2024-05-10 2024-06-08
1.6.1 Bug Fixes 1.6 15 2024-05-10 2024-05-24
1.6.2 Enhancements 1.6.1 10 2024-05-25 2024-06-05
1.6.3 Technical Support 1.6.2 5 2024-06-06 2024-06-08

Creating a GANTT chart is relatively easy once you complete your MS Project WBS.

Beginning with each work package in the WBS, you must add the following in MS Project.

1. Each task (work package) should be linked to its PREDECESSOR and SUCCESSOR tasks. You know you cannot start the job until predecessor tasks are completed. Each predecessor/successor must be identified in the MS Project.

2. Each task should be assigned a duration. That is, how long will it take to complete this task? This can be entered in minutes, hours, or days. But using the sametimeframe for all jobs in your plan would be best.

3. Each task should be assigned a start date.

4. Each task can optionally be assigned a resource in MS Project. That is, WHO will be doing the work.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

More Books

Students also viewed these General Management questions

Question

=+f) Give the degrees of freedom for the test.

Answered: 1 week ago

Question

Summarize group psychotherapy outcome research.

Answered: 1 week ago