Here is the information about the project: Activity Immediate Predecessors Optimistic Time Most Likely Time Pessimistic Time A N/A 2 3 4 B A 1
Here is the information about the project: Activity Immediate Predecessors Optimistic Time Most Likely Time Pessimistic Time A N/A 2 3 4 B A 1 2 5 C B 1 2 3 D A 1 2 3 E B 4 5 6 F B, C, D 2 4 6 G F 2 2