Question
Heritage Arboretum Development Project The team planning and managing the arboretum development project is composed mostly of volunteers but includes some township staff. Several volunteers
Heritage Arboretum Development Project
The team planning and managing the arboretum development project is composed mostly of volunteers but includes some township staff. Several volunteers have related professional experience and credentials such as certified arborist, master gardener, and landscape architect. Almost all of the volunteers have been through a two-year series of classes and assignments conducted by the state forester. Some of the staff have also studied under the state forester and each has experience in some aspect of the needed work.
1.How do you think the team members should estimate the amount of work they can accomplish during each iteration?
2.Should the team seek more volunteers? If so, how should they supervise them? Where should they seek additional volunteers? What stories should they have the volunteers work on?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access with AI-Powered Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started