Hi expert. Please provide the workflow and answer to the question in the picture. Geofff has budgeted to use RM 72,000 direct materials in October.
Hi expert. Please provide the workflow and answer to the question in the picture.
Geofff has budgeted to use RM 72,000 direct materials in October. When confirmation is available in November, Geoff discovers that the actual expenditure was RM 75,000. Calculate the total direct materials variance for OctoberStep by Step Solution