Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

Hi I just need help on the attached question! If you don't mind showing steps so I can see where I am going wrong, thanks!

Hi I just need help on the attached question! If you don't mind showing steps so I can see where I am going wrong, thanks!

image text in transcribed
507. A freestanding concrete wall that is 72 It long x 12 11 high x 1 ll thick is to be built in three equal placements. The following data apply: Exclude overhead and prot. Exclude wall bulkheads. CONSTRUCTION AFTERNOON SAMPLE QUESTIONS Material prices include all taxes and delivery. Include 10% waste on concrete. Labor Carpenter Laborer Supervisor Crews Erect and strip Place concrete The total cost of the wall is most nearly: (A) (B) {C} (D) $15,350 $19,170 $23,000 $25,670 $3 2 . 73H\" $26.08fhr $3 5 .3 7/1]: 4 carpenters 2 laborers I supervisor (working) 3 laborers 1 carpenter l supervisor (working) Productivity Erect forms 2.60 crewhoursftOG ftz Strip run-m,- 0.95 crewhoun'l f'lZ Place concrete 9.09 CrewhaurSr'IOO yeti M ale-rials Fonnwork, initial erection {liltir'f't2 Fonnwork, reuse $0.\".iu4ff't2 Concrete, Redi-Mix at site calmed\" Reinforcing subcontract $120.00rd3

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Modeling the Dynamics of Life Calculus and Probability for Life Scientists

Authors: Frederick R. Adler

3rd edition

840064187, 978-1285225975, 128522597X, 978-0840064189

More Books

Students also viewed these Mathematics questions