Question
Hi, I need help with some questions about SAFe framework What are two different types of Enabler Stories? (Choose two.) Feature Exploration Defects Infrastructure Impediment
Hi, I need help with some questions about SAFe framework
What are two different types of Enabler Stories? (Choose two.)
Feature
Exploration
Defects
Infrastructure
Impediment
An Agile Release Train (ART) has implemented a completely automated Continuous Integration/Continuous Delivery (CI/CD) pipeline that can deploy code as it is checked into the source-code repository. How might a Product Owner (PO) adjust team events to take advantage of this capability and promote the flow of value?
- Identify Stories that are cleared for automatic delivery during Iteration Planning
- Release Stories that have been included in the team demo
- Review and accept Stories as they are completed
- Implement Feature toggles to control which Stories are released
Product Management has content authority for the Program Backlog including: the Vision, the Roadmap, driving the PI Objectives, and what else?
- Working with business stakeholders and Solution and System Architects to implement holistic technology across Value Streams?
- Managing risk, helping to ensure value delivery, and driving continuous improvement
- Accepting Stories and team increments
- Establishing Features and benefit hypotheses?
Which statement characterizes the perspectives of the definition of done (DoD)?
- Product Owners focus on Features while Product Managers focus on Stories
- Product Owners focus on the release while Product Managers focus on the team increment
- Product Owners focus on the Iteration while Product Managers focus on the release
- Product Owners focus on the Solution while Product Managers focus on the team increment
Which statement is true about estimating and forecasting the Portfolio Backlog?
- Refinement is necessary when estimating the effort needed to implement an Epic
- Feature estimates are rolled up into Epic estimates
- Which role is primarily responsible for working with business teams
- WSJF is used to assign Epics to Value Streams Epic forecasting is based on the cost estimate
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started