Hi I need solution to the question below in OS please: Assume there are 6 processes with burst time and arrival time as shown below
Hi
I need solution to the question below in OS please:
Assume there are 6 processes with burst time and arrival time as shown below
PID | Arrival Time | Burst Time |
P1 | 0 | 4 |
P2 | 1 | 5 |
P3 | 2 | 2 |
P4 | 3 | 1 |
P5 | 4 | 6 |
P6 | 6 | 3 |
Time quantum = 2
Draw the Gant Chart
Calculate average waiting time, completion time, turnaround time for each processess execution.