Question
Hickory Company manufactures two products13,000 units of Product Y and 5,000 units of Product Z. The company uses a plantwide overhead rate based on direct
Hickory Company manufactures two products13,000 units of Product Y and 5,000 units of Product Z. The company uses a plantwide overhead rate based on direct labor-hours. It is considering implementing an activity-based costing (ABC) system that allocates all of its manufacturing overhead to four cost pools. The following additional information is available for the company as a whole and for Products Y and Z: |
Activity Cost Pool | Activity Measure | Estimated Overhead Cost | Expected Activity | ||
Machining | Machine-hours | $ | 231,600 | 12,000 | MHs |
Machine setups | Number of setups | $ | 55,900 | 130 | setups |
Production design | Number of products | $ | 77,000 | 2 | products |
General factory | Direct labor-hours | $ | 364,500 | 14,400 | DLHs |
Activity Measure | Product Y | Product Z |
Machine-hours | 6,300 | 5,700 |
Number of setups | 40 | 90 |
Number of products | 1 | 1 |
Direct labor-hours | 9,000 | 5,400 |
Required: | |||||||||||||
What is the activity rate for the Product Design activity cost pool?
|
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started