Hickory Company manufactures two products13,000 units of Product Y and 5,000 units of Product Z. The company uses a plantwide overhead rate based on direct labor-hours. It is considering implementing an activity-based costing (ABC) system that allocates all of its manufacturing overhead to four cost pools. The following additional information is available for the company as a whole and for Products Y and Z:
Activity Cost Pool | Activity Measure | Estimated Overhead Cost | Expected Activity |
Machining | Machine-hours | $ | 231,600 | 12,000 | MHs |
Machine setups | Number of setups | $ | 55,900 | 130 | setups |
Production design | Number of products | $ | 77,000 | 2 | products |
General factory | Direct labor-hours | $ | 364,500 | 14,400 | DLHs |
|
Activity Measure | Product Y | Product Z |
Machine-hours | 6,300 | 5,700 |
Number of setups | 40 | 90 |
Number of products | 1 | 1 |
Direct labor-hours | 9,000 | 5,400 |
|
referencesebook & resources
Required: |
What is the companys plantwide overhead rate? (Round your answer to 2 decimal places.) |
Predetermined overhead rate | | per DLH | |
Required: |
Using the plantwide overhead rate, how much manufacturing overhead cost is allocated to Product Y and Product Z? (Round your intermediate calculations to 2 decimal places and final answers to the nearest dollar amount.) |
| Product Y | Product Z | Manufacturing overhead allocated | | | |
Required: |
What is the activity rate for the Machining activity cost pool? (Round your answer to 2 decimal places.) |
|
Required: |
What is the activity rate for the Machine Setups activity cost pool? |
|
Required: |
What is the activity rate for the Product Design activity cost pool? |
|
Activity rate | | per product |
Required: |
What is the activity rate for the General Factory activity cost pool? (Round your answer to 2 decimal places.) |
|
Required: |
Which of the four activities is a batch-level activity? |
|
| Machine setups activity |
| Machining activity |
| Product design activity |
| General factory activity |
check my workreferencesebook & resources
Required: |
Which of the four activities is a product-level activity? |
|
| Product design activity |
| Machining activity |
| General factory activity |
| Machine setups activity |
Required: |
Using the ABC system, how much total manufacturing overhead cost would be assigned to Product Y? (Round your intermediate calculations to 2 decimal places and final answers to the nearest dollar amount.) |
Total manufacturing overhead cost | | |
Required: |
Using the ABC system, how much total manufacturing overhead cost would be assigned to Product Z? (Round your intermediate calculations to 2 decimal places.) |
Total manufacturing overhead cost | | |
Required: |
Using the plantwide overhead rate, what percentage of the total overhead cost is allocated to Product Y and Product Z? (Round your "Percentage" answer to 1 decimal place. (i.e. .1234 should be entered as 12.3)) |
| Product Y | | Product Z | | Manufacturing overhead | | % | | % | |
Required: |
Using the ABC system, what percentage of the Machining costs is assigned to Product Y and Product Z? (Round your answers to 2 decimal places.) |
| | Product Y | | Product Z | | Machining cost | | % | | % | | |
Required: |
Using the ABC system, what percentage of Machine Setups cost is assigned to Product Y and Product Z? (Round your answers to 2 decimal places.) |
|
| Product Y | | Product Z | |
Machine Setups cost | | % | | % |
Required: |
Using the ABC system, what percentage of the Product Design cost is assigned to Product Y and Product Z? (Round your answers to 2 decimal places.) |
| | | Product Y | | Product Z | | Product design cost | | % | | % | | |
Required: |
Using the ABC system, what percentage of the General Factory cost is assigned to Product Y and Product Z? (Round your "Percentage" answer to 1 decimal place. (i.e. .1234 should be entered as 12.3)) | Product Y | | Product Z | | General factory cost | | % | | % | |
| | | | | | | | | |